Arizona DOT Right-of-Way Resolutions
Resolution Number:
Highway:
District:
Tracs:
Project:
Resolution date:
Section:
The Gap - City of Page
County:
Type:
Old Route:
Cur Rte Code:
Current Route:
Comment:
Establishment of existing 44 miles of Indian Route 20 as Temporary U.S. Route 89 (89T) for traffic diversion during the reconstruction of U.S. Route 89 due to the landslide of February 20, 2013 which occurred 18 miles south of Page. Temporary U.S. Route 89 will be relinquished upon the reopening and reconstruction of U.S. Route 89 between Bitter Springs and Page. This establishment herein allows ADOT to negotiate an easement with the Navajo Nation. See file for more information.
978: